Kingsley Wastewater Treatment Plant

Kingsley, IA | Public Works

Overview

ISG designed the retrofit of existing wastewater treatment lagoons for the City of Kingsley, enabling more compliant and higher capacity wastewater treatment processes.


Opportunity

Anticipating growth over a 20-year planning period and with its wastewater treatment facilities no longer able to keep up with local standards, the City of Kingsley needed a water solutions partner to design system updates.

Solution

The City of Kingsley’s existing continuous discharge aerated lagoon was not capable of meeting NPDES effluent limits after changes were made to Iowa’s water quality standards. Following a detailed alternatives analysis, ISG recommended retrofitting the existing wastewater treatment lagoons using a Submerged Attached Growth Reactor (SAGR). The SAGR is primarily designed to provide nitrification (ammonia removal) in cold to moderate climates. The SAGR consists of a submerged gravel bed with evenly distributed wastewater flow across the width of the cell providing the necessary surface area for growth and attachment of a nitrifying biomass within the bed. The gravel bed is covered with a layer of peat or mulch for insulation. Aeration throughout the floor of the SAGR provides aerobic conditions that are required for nitrification. An effluent ultraviolet disinfection system also allows the City to meet more stringent bacterial limits during summer months.

Since the Iowa Wastewater Facilities Design Standards did not specifically address the SAGR type process, the Iowa DNR had to perform a technology analysis in order for Kingsley to proceed with the project. Based on the IDNR review, the SAGR system was approved as an acceptable alternative technology, and the City of Kingsley proceeded with one of the first installations in Iowa using the SAGR technology.

Market News

Lake Crystal ramping up water quality improvement efforts

November 14, 2019 – LAKE CRYSTAL, Minn. (KEYC) — Water quality concerns in Lake Crystal are being addressed thanks to a group effort and the addition of a phosphorus removal system installed in Lake Crystal which is the first to be installed in the state.
Read More

$15 Million BUILD Grant Announced for Central Iowa Water Trails

November 7, 2019 – The Des Moines Area Metropolitan Planning Organization (MPO), together with its partners working to implement Central Iowa Water Trails, today announces its receipt of a $25 million grant from the Better Utilizing Investments to Leverage Development, or BUILD, grant program of the U.S. Department of Transportation.
Read More